Breaking News
N. Sembilan Umno bloc withdraws support for MB Aminuddin Harun, claims loss of confidence
KUALA LUMPUR, April 27 — Negeri Sembilan Umno chairman Datuk Seri Jalaluddin Alias said all 14
...Witness recounts deadly Ulu Tiram police station attack
KUALA LUMPUR, April 9 — A police corporal in the Ulu Tiram police station attack case
...KL High Court told Fahmi made no political speech at Rawang mosque
KUALA LUMPUR, April 9 — An investigating officer told the High Court yesterday that Communications Minister
...Madani Mart uses licensing model, not govt-funded, says deputy minister amid KR1M comparisons
JOHOR BAHRU, April 5 — Madani Mart operates on a licensing model in collaboration with entrepreneurs
...Anwar pays tribute to Ling Liong Sik, says nation loses a ‘dedicated leader’
KUALA LUMPUR, April 5 — Prime Minister Datuk Seri Anwar Ibrahim has expressed condolences over the
...Genting Highlands restaurant charges RM902 for fish dish, draws KPDN scrutiny
KUALA LUMPUR, March 29 — A Genting Highlands restaurant has reportedly come under scrutiny after a group
...
MRT Corp addresses public concerns over Penang LRT project timeline
KUALA LUMPUR, April 21 — MRT Corp has clarified that the Penang LRT Mutiara Line is moving forward as planned, following questions over the pace of progress.
In a statement yesterday, the agency said it obtained official clearance for advance works under Section 20A of the Town and Country Planning Act on April 15.
This follows a three-month period of activity which also saw MRT Corp securing access to 86 land plots, ahead of its expected timeline.
It said this milestone, made possible through the Land Acquisition Act, demonstrates steady advancement in the project.
“Over the past three months, MRT Corp has been actively driving the project forward,” the government-linked company said.
SRS Consortium, the appointed civil contractor, is in the midst of fulfilling contractual conditions before receiving the green light to begin work.
Only once the Notice to Proceed is issued can SRS finalise civil engineering plans and begin relocating utilities in preparation for construction, the firm said.
MRT Corp reiterated its commitment to transparency and progress and asked for continued public support as the project enters its next phase.
Targeted to link key residential, commercial, and industrial zones from Komtar to the Penang International Airport and beyond, the Mutiara Line is part of the state’s long-term transport master plan.